===== PDF PAGE 56 ===== [Extraction: embedded PDF text] CITY OF WEST CHICAGO . INFRASTRUCTURE COMMITTEE AGENDA ITEM SUMMARY ITEM TITLE: AGENDA ITEM NUMBER: _4__._""""• _·+=.............__ Resolution No. 22-R-0075 - Execution of Joint Funding COMMITTEE AGENDA DATE: December 1, 2022Agreement for State-Let Construction Work with Illinois COUNCIL AGENDA DATE: December 19, 2022Department of Transportation and Local Match Appropriation for Construction Costs Associated with the Technology Boulevard Resurfacing Project STAFF REVIEW: Mehul T. Patel, P.E. , CFM., Director of Public Works SIGNATURE MJ r~r~ APPROVED BY CITY ADMINISTRATOR: Michael L. Guttman SIGNATURE._________ _ ITEM SUMMARY: Technology Boulevard Resurfacing Project (Project) between Fabyan Parkway and Roosevelt Road (IL-38) is targeted for March 10, 2023, Illinois Department of Transportation (I DOT) letting with construction anticipated to begin in the summer of 2023. The project is federally funded through the region's Surface Transportation Program (STP), administered by IDOT, with matching local funds from the City's Motor Fuel Tax (MFT) Fund. The estimated construction cost for the Project is $1,008,455.89. The City received 80% federal funds or an amount not to exceed $887,441 for both Construction and Construction Engineering (CE). The Project consists of pavement milling and resurfacing, partial-depth pavement patching, intermittent curb and gutter replacement, ADA curb ramp upgrades, and pavement markings. Final plans, specifications, and estimates are anticipated to be submitted to IDOT on November 28, 2022. As part of the project implementation process, prior to IDOT letting, the City is required to approve and execute the Joint Funding Agreement for State-Let Construction Work (BLR 05310C) with IDOT. The agreement must also include the passage of a Resolution appropriating City's local match associated with the project. At this time, the local match is estimated to be $201,691.18. The exact amount of City's local match will be determined at the completion of the project closeout. The FY 2023 Proposed Budget includes $285,600 under the Motor Fuel Tax Fund (16-34-58-4807) for construction costs. Unlike construction engineering, where the initial costs have to be paid for by the City, the construction costs are paid for by IDOT and the City will be invoiced throughout the project for its local match. ACTIONS PROPOSED: Approve Resolution No. 22-R-0075 authorizing the Mayor to execute the Joint Funding Agreement for State-Let Construction Work (SLR 0531 OC) and appropriating the local match in the amount of $201,691.18 for construction costs associated with the Technology Boulevard Resurfacing Project. COMMITTEE RECOMMENDATION: ===== PDF PAGE 57 ===== [Extraction: embedded PDF text] ~Illinois Department Joint Funding Agreement for of Transportation State-Let Construction WorkW LOCAL PUBLIC AGENCY ..=L=oc=a::.:..l..:..P=ub::.;.li=c..:..A=ge=n.;..;;c;.L.y___________________ ~ ..-=C-=-o=un"""ty....______ __, Section Number ._lc_it_y_o_fW_ e_st_C_hi_ca_g_o_______________ __.l._ID_u_P_ag_e_ ___ ~ll20-00085-00-RS r-F-=-u'""nd=-T..:...Yu:P-=-e----------~ ITEP, SRTS, HSIP Number(s) MPO Name MPO TIP Number _lsT_U~~~~~~~ll~~=========:-=--=--=--=--=1~1~cM=A=P===1 ~loa_-2_0-0_03_8~~-' Construction ""'S"""'ta-'-te"'"""J"'"'o""'"b-'-N""'-u_m-'-b=er__ _., Project Number ~lc_-9_1-_15_8-_2_2 _ __.li_KC_B_A_(2_90_) __ __, [gl Construction on State Letting [gl Construction Engineering D Utilities D Railroad Work This Agreement is made and entered into between the above local public agency, hereinafter referred to as the "LPA" and the State of Illinois, acting by and through its Department of Transportation, hereinafter referred to as "STATE". The STATE and LPA jointly propose to improve the designated location as described below. The improvement shall be consulted in accordance with plans prepared by, or on behalf of the LPA and approved by the STATE using the STATE's policies and procedures approved and/or required by the Federal Highway Administration, hereinafter referred to as "FHWA". LOCATION Stationing rL_oc_a_l_S_tre_e_U_R_o_ad_Na_m_e_____ --. ~K_ey~R_o_u_te______ --,rL_en_g~th______ ~From ~T_o ___ ~ ~IT_ec_hn_o_lo_gy_B_o_ul_ev_a_rd___ __.l~l12_6_0~~~~~_,l~lo._23_m_i_le~~~_,l=lo.=oo====l~lo._23_ __. Location Termini IL Route 38 (Roosevelt Road) to Innovation Drive/Discovery Drive ""'C'""u'"""rre""'n""'t"""J=ur"""is-"-d""ic""tio"""n'--------------------. FE'""x i~st"'"in"'--"S""'tr""'uc"""tu""'"r'"""e-'-N'"""u-'-m'"""be=r.....,s..,_ __ __, j Add Location I '~C_it_y_o_f_W_e_s_t_C_h_i_ca_g_o_ _______________ ~l~N_IA________ __ _,I Remove I LOCATION Stationing rL_oc_a_l_S_tre_e_U_R_o_ad_Na_m_e_____ --. ~K_ey~R_o_u_te______ --,rl_en_g~th______ ~~F_ro_m__ ~~T_o ___ ~ lo.33 mile llo.oo _ __.l~re_c_hn_o_lo_gy_B_o_ul_ev_a_rd___ __.l 11261 I I~lo._33 Location Termini Innovation Drive/Discovery Drive to Innovation Drive/Discovery Drive ~C_u_rre~n_t_J_ur_is_d_ic_tio_n__________________ _, ~Ex_i_st_in_s_tr_uc_tu_r_e_N_u_m_be_r~s..._ __ __, j Add Location I .....lc_it_y_o_f_W_e_s_t_C_h_ic_a_g_o _ __________ ____ __.l .....N_IA_ ________ ___.I Remove I LOCATION Stationing rL_oc_a_l_S_tre_e_U_R_o_ad_Na_m_e_____ --.~K-'-ey~R_o..:..u~re'--------.~Le..:..n~g~th'--------.~F_ro_m__ --.~T_o ___ ~ lo.23 mile lo.oo _ __.~IT_ec_h_no_lo_gy_B_o_ul_ev_a_rd_ __ __.117262 I I I~lo._23 Location Termini Innovation Drive/Discovery Drive to E. Fabyan Parkway ~C_u_rre_n_t_Ju_r_is_d_ic_tio_n__________________ -----. r=Ex:.:.:1.::..:st::.:..in~S=tr=uc=t=ur=e...:...N=u'-"m=be=r..i.:s"'-----, l Add Location I ~lc_icy_o_f_W_e_s_t_C_h_ic_a_g_o_____________ __ ___.l .....N_IA_________ ___.I Remove I PROJECT DESCRIPTION The improvement consists of cold milling bituminous surface removal and resurfacing with HMA Leveling Binder and Surface Course, partial-depth pavement patching, intermittent curb and gutter replacement, ADA curb ramp upgrades, and pavement markings. LOCAL PUBLIC AGENCY APPROPRIATION· REQUIRED FOR STATE LET CONTRACTS Printed 11/17/22 Page 1 of 7 BLR 0531 OC (Rev. 03/31/22) ===== PDF PAGE 58 ===== [Extraction: embedded PDF text] By execution of this Agreement the LPA attests that sufficient moneys have been appropriated or reserved by resolution or ordinance to fund the LPA share of project costs. A copy of the authorizing resolution or ordinance is attached as an addendum. METHOD OF FINANCING - (State-Let Contract Work Only) Check One 0 METHOD A - Lump Sum (80% of LPA Obligation --------- Lump Sum Payment - Upon award of the contract for this improvement, the LPA will pay the STATE within thirty (30) calendar days of billing, in lump sum, an amount equal to 80% of the LPA's estimated obligation incurred under this agreement. The LPA will pay to the STATE the remainder of the LPA's obligation (including any nonparticipating costs) in a lump sum within thirty (30) calendar days of billing in a lump sum, upon completion of the project based on final costs. 0 METHOD B - Monthly Payments of due by the of each successive month. Monthly Payments - Upon award of the contract for this improvement, the LPA will pay to the STATE a specified amount each month for an estimated period of months, or until 80% of the LPA's estimated obligation under the provisions of the agreement has been paid. The LPA will pay to the STATE the remainder of the LPA's obligation (including any nonparticipating costs) in a lump sum, upon completion of the project based upon final costs. divided by estimated total cost multiplied by actual progress payment. IZJ METHOD C - LPA's Share _ ___B_A_L_A_N_C_E____ Progress Payments - Upon receipt of the contractor's first and subsequent progressive bills for this improvement, the LPA will pay to the STATE within thirty (30) calendar days of receipt, an amount equal to the LPA's share of the construction cost divided by the estimated total cost multiplied by the actual payment (appropriately adjust for nonparticipating costs) made to the contractor until the entire obligation incurred under this agreement has been paid. Failure to remit the payment(s) in a timely manner as required under Methods A, B, or C shall allow the STATE to internally offset, reduce, or deduct the arrearage from any payment or reimbursement due or about to become due and payable from the STATE to the LPA on this or any other contract. The STATE at its sole option, upon notice to the LPA, may place the debit into the Illinois Comptroller's Offset System (15 ILCS 405/10.05) or take such other and further action as may be required to recover the debt. THE LPA AGREES: 1. To acquire in its name, or in the name of the STATE if on the STATE highway system, all right-of-way necessary for this project in accordance with the requirements of Titles II and Ill of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, and established State policies and procedures. Prior to advertising for bids, the LPA shall certify to the STATE that all requirements of Titles II and Ill of said Uniform Act have been satisfied. The disposition of encroachments, if any, will be cooperatively determined by representatives of the LPA, the STATE, and the FHWA if required. 2. To provide for all utility adjustments and to regulate the use of the right-of-way of this improvement by utilities, public and private, in accordance with the current Utility Accommodation Policy for Local Public Agency Highway and Street Systems. 3. To provide for surveys and the preparation of plans for the proposed improvement and engineering supervision during construction of the proposed improvement. 4. To retain jurisdiction of the completed improvement unless specified otherwise by addendum (addendum should be accompanied by a location map). If the improvement location is currently under road district jurisdiction, a jurisdictional addendum is required. 5. To maintain or cause to be maintained the completed improvement (or that portion within its jurisdiction as established by addendum referred to in item 4 above) in a manner satisfactory to the STATE and the FHWA. 6. To comply with all applicable Executive Orders and Federal Highway Acts pursuant to the Equal Employment Opportunity and Nondiscrimination Regulations required by the U.S. Department of Transportation. 7. To maintain for a minimum of 3 years after final project close out by the STATE, adequate books, records and supporting documents to verify the amounts, recipients and uses of all disbursements of funds passing in conjunction with the contract. The contract and all books, records, and supporting documents related to the contract shall be available for review and audit by the Auditor General and the STATE. The LPA agrees to cooperate fully with any audit conducted by the Auditor General, the STATE, and to provide full access to all relevant materials. Failure to maintain the books, records, and supporting documents required by this section shall establish presumption in favor of the STATE for recovery of any funds paid by the STATE under the contract for which adequate books, records and supporting documentation are not available to support their purported disbursement. 8. To provide if required, for the improvement of any railroad-highway grade crossing and rail crossing protection within the limits of the proposed improvement. 9. To comply with Federal requirements or possibly lose (partial or total) Federal participation as determined by the FHWA. 10. To provide or cause to be provided all of the initial funding , equipment, labor, material, and services necessary to complete locally administered portions of the project. 11 . (Railroad Related Work) The LPA is responsible for the payment of the railroad related expenses in accordance with the LPN railroad agreement prior to requesting reimbursement from the STA TE. Requests for reimbursement should be sent to the appropriate IDOT District Bureau of Local Roads and Streets Office. Engineer's Payment Estimates shall be in accordance with the Division of Cost. Printed 11/17/22 Page 2 of 7 BLR 0531 QC (Rev. 03/31/22) ===== PDF PAGE 59 ===== [Extraction: embedded PDF text] 12. Certifies to the best of its knowledge and belief that it's officials: a. are not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from covered transactions by any Federal department or agency; b. have not within a three-year period preceding this agreement been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State anti-trust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements receiving stolen property; c. are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, Local) with commission of any of the offenses enumerated in item (b) of this certification; and d. have not within a three-year period preceding the agreement had one or more public transactions (Federal, State, Local) terminated for cause or default. 13. To include the certifications, listed in item 12 above, and all other certifications required by State statutes, in every contract, including procurement of materials and leases of equipment. 14. That execution of this agreement constitutes the LPA's concurrence in the award of the construction contract to the responsible low bidder as determined by the STATE. 15. That for agreements exceeding $100,000 in federal funds, execution of this agreement constitutes the LP A's certification that: a. No federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any agency, a member of congress, an officer or employee of congress, or any employee of a member of congress in connection with the awarding of any federal contract, the making of any cooperative agreement, and the extension, continuation, renewal, amendment or modification of any Federal contract, grant, loan or cooperative agreement. b. If any funds other than federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a member of congress, an officer or employee of congress or an employee of a member of congress in connection with this federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit standard form - LLL, "Disclosure Form to Report Lobbying", in accordance with its instructions. c. The LPA shall require that the language of this certification be included in the award documents for all subawards (including subcontracts, subgrants and contracts under grants, loans, and cooperative agreements), and that all subrecipients shall certify and disclose accordingly 16. To regulate parking and traffic in accordance with the approved project report. 17. To regulate encroachments on public rights-of-way in accordance with current Illinois Compiled Statutes. 18. To regulate the discharge of sanitary sewage into any storm water drainage system constructed with this improvement in accordance with the current Illinois Compiled Statutes. THE STATE AGREES: 1. To provide such guidance, assistance, and supervision to monitor and perform audits to the extent necessary to assure validity of the LPA's certification of compliance with Title II and Ill Requirements. 2. To receive bids for construction of the proposed improvement when the plans have been approved by the STATE (and FHWA, if required) and to award a contract for construction of the proposed improvement after receipt of a satisfactory bid. 3. To provide all initial funding and payments to the contractor for construction work let by the STATE. The LPA will be invoiced for their share of contract costs per the method of payment selected under Method of Financing based on the Division of Costs shown on Addendum 2. 4. For agreements with federal and/or state funds in construction engineering, utility work and/or railroad work: a. To reimburse the LPA for federal and/or state share on the basis of periodic billings, provided said billings contain sufficient cost information and show evidence of payments by the LPA; b. To provide independent assurance sampling and furnish off-site material inspection and testing at sources normally visited by STATE inspectors for steel, cement, aggregate, structural steel, and other materials customarily tested by the STATE. IT IS MUTUALLY AGREED: 1. Construction of the project will utilize domestic steel as required by Section 106.01 of the current edition of the Standard Specifications for Road and Bridge Construction and federal Buy America provisions 2. That this Agreement and the covenants contained herein shall become null and void in the event that the FHWA does not approve the proposed improvement for Federal-aid participation within one (1) year of the date of execution of this agreement. 3. This agreement shall be binding upon the parties, their successors, and assigns. 4. For contracts awarded by the LPA, the LPA shall not discriminate on the basis of race, color, national origin or sex in the award and performance of any USDOT - assisted contract or in the administration of its DBE program or the requirements of 49 CFR part 26. The LPA shall take all necessary and reasonable steps under 49 CFR part 26 to ensure nondiscrimination in the award and administration of USDOT - assisted contracts. The LPA's DBE program, as required by 49 CFR part 26 and as approved by USDOT, is incorporated by reference in this agreement. Upon notification to the recipient of its failure to carry out its approved Printed 11/17/22 Page 3 of 7 BLR 05310C (Rev. 03/31/22) ===== PDF PAGE 60 ===== [Extraction: embedded PDF text] program, the STATE may impose sanctions as provided for under part 26 and may, in appropriate cases, refer the matter for enforcement under 18 U.S. C 1001 and/or the Program Fraud Civil Remedies Act of 1986 (31 U.S.C 3801 et seq.). In the absence of a US DOT - approved LPA DBE Program or on state awarded contracts, this agreement shall be administered under the provisions of the STATE'S USDOT approved Disadvantaged Business Enterprise Program. 5. In cases where the STATE is reimbursing the LPA, obligation of the STATE shall cease immediately without penalty or further payment being required if, in any fiscal year, the Illinois General Assembly or applicable federal funding source fails to appropriate or otherwise make available funds for the work contemplated herein. 6. All projects for the construction of fixed works which are financed in whole or in part with funds provided by this agreement and/or amendment shall be subject to the Prevailing Wage Act (820 ILCS 130/0.01 et seq.) unless the provisions of the act exempt its application. FISCAL RESPONSIBILITIES: 1. Reimbursement Requests: For reimbursement requests the LPA will submit supporting documentation with each invoice. Supporting documentation is defined as verification of payment, certified time sheets or summaries, vendor invoices, vendor receipts, cost plus fix fee invoice, progress report, personnel and direct cost summaries, and other documentation supporting the requested reimbursement amount (Form BLR 05621 should be used for consultant invoicing purposes). LPA invoice requests to the STATE will be submitted with sequential invoice numbers by project. 2. Financial Integrity Review and Evaluation (FIRE) program: LPA's and the STATE must justify continued federal funding on inactive projects. 23 CFR 630.106(a)(5) defines an inactive project as a project which no expenditures have been charged against Federal funds for the past twelve (12) months. To keep projects active, invoicing must occur a minimum of one time within any given twelve (12) month period. However, to ensure adequate processing time, the first invoice shall be submitted to the STATE within six (6) months of the federal authorization date. Subsequent invoices will be submitted in intervals not to exceed six (6) months. 3. Final Invoice: The LPA will submit to the STATE a complete and detailed final invoice with applicable supporting documentation of all incurred costs, less previous payments, no later than twelve ( 12) months from the date of completion of work or from the date of the previous invoice, whichever occurs first. If a final invoice is not received within this time frame, the most recent invoice may be considered the final invoice and the obligation of the funds closed. Form BLR 05613 (Engineering Payment Record) is required to be submitted with the final invoice for engineering projects. 4. Project Closeout: The LPA shall provide the final report to the appropriate STATE district office within twelve (12) months of the physical completion date of the project so that the report may be audited and approved for payment. If the deadline cannot be met, a written explanation must be provided to the district prior to the end of the twelve (12) months documenting the reason and the new anticipated date of completion. If the extended deadline is not met, this process must be repeated until the project is closed. Failure to follow this process may result In the immediate close-out of the project and loss of further funding. 5. Project End Date: The period of performance (end date) for state and federal obligation purposes is five (5) years for projects under $1,000,000 or seven (7) years for projects over $1,000,000 from the execution date of the agreement. Requests for time extensions and joint agreement amendments must be received and approved prior to expiration of the project end date. Failure to extend the end date may result in the immediate close-out of the project and loss of further funding. 6. Single Audit Requirements: If the LPA expends $750,000 or more a year in federal financial assistance, they shall have an audit made in accordance with 2 CFR 200. LPA's expending less than $750,000 a year shall be exempt from compliance. A copy of the audit report must be submitted to the STATE (IDOT's Office of Internal Audit, Room 201, 2300 South Dirksen Parkway, Springfield, Illinois, 62764) within 30 days after the completion of the audit, but no later than one year after the end of the LPA's fiscal year. The CFDA number for all highway planning and construction activities is 20.205. Federal funds utilized for construction activities on projects let and awarded by the STATE (federal amounts shown as "Participating Construction" on Addendum 2) are not Included in a LPA's calculation of federal funds expended by the LPA for Single Audit purposes .. 7. Federal Registration: LPA's are required to register with the System for Award Management or SAM, which is a web-enabled government-wide application that collects, validates, stores, and disseminates business Information about the federal government's trading partners in support of the contract award and the electronic payment processes. To register or renew, please use the following website: httos:/twww.sam.gov/SAM/ 8. Required Uniform Reporting: For work not included on a state letting, the Grant Accountability and Transparency Act (30 ILCS 708) requires a uniform reporting of expenditures. Uniform reports of expenditures shall be reported no less than quarterly using IDOT's BoBS 2832 form available on IDOT's web page under the "Resources" tab. Additional reporting frequency may be required based upon specific conditions or legislation as listed In the accepted Notice of State Award (NOSA). Specific conditions are based upon the award recipient/grantee's responses to the Fiscal and Administrative Risk Assessment (ICQ) and the Programmatic Risk Assessment (PRA) .. NOTE: Under the terms of the Grant Funds Recovery Act (30 ILCS 705/4.1 ), "Granter agencies may withhold or suspend the distribution of grant funds for failure to file requirement reports" if the report is more than 30 calendar days delinquent, without any approved written explanation by the grantee, the entity will be placed on the Illinois Stop Payment List. (Refer to the Grantee Compliance Enforcement System for detail about the Illinois Stop Payment List: https://www.illinois.gov/sites/GATA/ Pages/ Resourcelibrary.aspx) Printed 11117/22 Page 4 of 7 SLR 05310C (Rev. 03/31/22) ===== PDF PAGE 61 ===== [Extraction: embedded PDF text] ADDENDA Additional information and/or stipulations are hereby attached and identified below as being a part of this agreement. 1. Location Map 181 2. Division of Cost 181 181 3. Resolution* D 4. •Appropriation and signature authority resolution must be in effect on, or prior to, the execution date of the agreement. Printed 11/17/22 Page 5 of7 BLR 0531 OC (Rev. 03/31/22) ===== PDF PAGE 62 ===== [Extraction: embedded PDF text] The LPA further agrees as a condition of payment, that it accepts and will comply with the applicable provisions set forth in this agreement and all Addenda indicated above. APPROVED Local Public Agency Name of Official Print or T e Name Ruben Pineda Title of Official MayorI The above signature certifies the agency's TIN number is 366006144 conducting business as a Governmental Entity. DUNSNumber113554448 UEI LQLNCLHFMNJ4 APPROVED State of Illinois Department of Transportation .__IO_m_e_r_O_s_m_a_n_, _P_.E_._· -Se_c_r-et_a_ry_o_f_T-ra_n_s_p_o-rta- t-io_n_ _ _ ___ ___.IO By: r...:;,,,,:e;,,;:oc...rg'1..;:e;,,,,;A'"".'""T;...;:a.p=a=s,"""P-'.-=E"".•....;:S;.:.,.E=·:.i...•-=E""ng""'i.;..:.ne;:..;e:;.;,r....;:o;.;..f -=L.::..oc=-=a"'-1 ..;..R=o=ad=s'-&;:;;....::S""'tr..::.e.::..ets=--~IO '-S-te-:o-1h_e_n_M_._T-ra-v-ia_ P_._E_. -D-ir-e-ct_o_ro-f-H-io_h_w_a_w_:s_P_lf_C_h_ie_f_E_n_oi_n_ee_r_ _, O I...:Y~a~n~gs~u'-K~i~m~· ....;:C;.;..h~i e;.:.,f....;:C;..;:o-=u.;..:.ns;:..;e;.:.,l __ ~~---------~IO l...:V~ic~k~iWc...=il.::..so:;.;,n~,....;:C;.;..h~i e;.:.,f;.;..F~is=c=al'--O;:..;ffi~1.::..ce:;.;,r~~---------~IO NQif;, A resolution authorizing the local official (or their delegate) to execute this agreement and appropriation of local funds is required to be attached as an addendum. The resolution must be approved prior to, or concurrently with, the execution of this agreement. If BLR 09110 or BLR 09120 are used to appropriate local matching funds, attach these forms to the signature authorization resolution. D Please check this box to open a fillable Resolution Form within this Addenda. Printed 11 /17 /22 Page 6 of 7 BLR 0531 0C (Rev. 03/31 /22) ===== PDF PAGE 63 ===== [Extraction: OCR (rendered-page OCR)] ADDENDA 1 PROJECT LOCATION MAP BEGIN PROJECT: : Be EABYAN PARKWAY | ' ===== PDF PAGE 64 ===== [Extraction: embedded PDF text] ADDENDA NUMBER 2 Local Public Agency County Section Number State Job Number ~P_ro...._je_ct_N_u_m_be_r____ ~ lcity of West Chicago llouPage 1120-000SS-OO-RS llc-91-158-22 llKCBA(290) I DIVISION OF COST Federal Funds State Funds Local Public Agency Type of Work Fund Type Amount % Fund Type Amount % Fund Type Amount % Totals Participating Construction STU $806,765.00 80% Local $201,691.00 20% $1,008,456.00 Construction Engineering STU $80,676.00 80% Local $20,169.00 20% $100,845.00 Total $887,441.00 Total Total $221,860.00 $1, 109,301.00 NOTE: The costs shown in the Division of Cost table are approximate and subject to change. The final LPA share is dependent on the final Federal and State participation. The actual costs will be used in the final division of cost for billing and reimbursement. Printed 11117122 Page 7 of 7 BLR 05310C (Rev. 03131122) ===== PDF PAGE 65 ===== [Extraction: embedded PDF text] ADDENDA3 RESOLUTION NO. 22-R-0075 A RESOLUTION AUTHORIZING THE MAYOR TO EXECUTE THE JOINT FUNDING AGREEMENT FOR STATE-LET CONSTRUCTION WORK AND APPROPRIATING THE LOCAL MATCH FOR CONSTRUCTION COSTS ASSOCIATED WITH THE TECHNOLOGY BOULEVARD RESURFACING PROJECT Section No.: 20-00085-00-RS Job No.: C-91-158-22 Project No.: KCBAC290) WHEREAS, the City of West Chicago is proposing to improve Technology Boulevard between Fabyan Parkway and Roosevelt Road (IL-38) in DuPage County, Illinois. WHEREAS, the above stated improvement will necessitate the use of funding provided through the Illinois Department of Transportation (IDOT); and signee WHEREAS, the use of these funds requires a joint funding agreement (AGREEMENT) with IDOT; and WHEREAS, the improvements require matching local funds; and NOW, THEREFORE, be it resolved by the City Council: SECTION 1: The City Council hereby appropriates $201,691.18, Two Hundred One Thousand Six Hundred Ninety-One Dollars and Eighteen Cents or as much as may be needed to match the required funding to complete the proposed improvements and furthermore agree§ to pass a supplemental resolution if necessary to appropriate additional funds for completion of the project. SECTION 2: This resolution will become Addenda 3 of the AGREEMENT. SECTION 3: The City of West Chicago is directed to transmit 3 (three) copies of the AGREEMENT and Resolution to IDOT District 1 Bureau of Local Roads and Streets. BE IT FURTHER RESOLVED that the Mayor is hereby authorized to execute an AGREEMENT with IDOT for the above-mentioned project and any other such documents related to the advancement and completion of said project. ===== PDF PAGE 66 ===== [Extraction: embedded PDF text] APPROVED this 19th day of December 2022. AYES: NAYES: ABSTAIN: ABSENT: Mayor Ruben Pineda ATTEST: Executive Office Assistant Valeria Perez