===== PDF PAGE 44 ===== [Extraction: embedded PDF text] CITY OF WEST CHICAGO INFRASTRUCTURE COMMITTEE AGENDA ITEM SUMMARY ITEM TITLE: AGENDA ITEM NUMBER: :::,rs~ Resolution No. 25-R-0042 - Contract Award - F.E. Moran, COMMITTEE AGENDA DATE: June 5, 2025Inc. for the Police Station HVAC Improvements Project for a COUNCIL AGENDA DATE: June 16, 2025Base Bid and Alternate No. 1 in an Amount Not to Exceed $923,000.00 and Reject Alternate No. 2 STAFF REVIEW: Mehul T. Patel, P.E., CFM- Director of Public Works SIGNATURE ITEM SUMMARY: The Police Station HVAC Improvements Project includes improvements to the heating, ventilation, and air conditioning (HVAC) at the Police Station located at 325 Spencer Street, as denoted in the enclosed location map. The scope of the project for Base Bid includes select demolition, HVAC rooftop unit (RTU) equipment replacement, boiler replacement, roof patching, temperature controls, variable air volume(VAV) box reuse, acoustical ceilings repairs, painting, necessary electrical work, and other associated work to complete the project. Alternate 1 includes upgrading the existing VAV controls, associated control valves, and ceiling repairs as required. Alternate 2 includes replacement ofVAV & fan-powered boxes and associated controls, complete with electrical wiring, and ceiling repairs as required. The Project is anticipated to be completed in November 2025, pending material availability. The Project was advertised for public bids in the Daily Herald and on an online bidding platform, QuestCDN, on April 29, 2025. A non-mandatory pre-bid meeting took place on-site on May 8, 2025. Staff opened bids on May 21, 2025, and below are the results: BASE BID+ BASE BID+ BASE BID+ BASE BID ALT. NO.1 ALT. NO. 2 CONTRACTOR ALT. NO.1 ALT. NO. 2 ALT. NO.1 AMOUNT AMOUNT AMOUNT AMOUNT AMOUNT RANK F.E. Moran, Inc. $720,000.00 $203 000.00 $465,000.00 $923,000.00 $1 ,185,000.00 1 Helm Mechanical $747,000.00 $238,000.00 $628,000.00 $985,000.00 $1,375,000.00 2 Voris Mechanical, Inc. $774,400.00 $233,500.00 $558,100.00 $1,007,900.00 $1 ,332,500.00 3 Amber Mechanical Contractors, Inc $883 800.00 $317,000.00 $647,800.00 $1 ,200,800.00 $1 531 ,600.00 4 1 Source Mechanical, Inc. $574,000.00 $196,000.00 $620,000.00 $770,000.00 $1 ,194,000.00 N/A * Commercial Mechanical, Inc. $604,000.00 $230,000.00 $603,000.00 $834,000.00 $1 ,207,000.00 NIA* BUDGETED AMOUNT $1 000 000.00 - * Bid deemed irresponsible and incomolete UDon contractor scoDe review. Bidder disqualified. Kluber, Inc., the City's Phase II and Ill Architect, completed a contractor scoping review for the Base Bid and Alternate No. 1 with the first two apparent low bidders, 1 Source Mechanical, Inc. and Commercial Mechanical Inc. Upon scoping review with the two contractors, their submitted bids were found to be incomplete as both contractors failed to include the $85,000 allowance in their Base Bid as required by contract specification; therefore, the bids were deemed irresponsible and bids were disqualified. The third low bidder, F.E. Moran, Inc. of Northbrook, Illinois, submitted a complete and qualified bid in the amount of $923,000.00, which is $77,000.00 or 7.7% lower than the budgeted amount of $1,000,000.00. After scope discussions with Kluber, Inc. and Facilities Maintenance staff, the Base Bid plus Alternate No. 2 were not taken into consideration for the project, as the lowest bid from F.E. Moran, Inc. was $185,000.00 or 18.5% over the budget amount of $1,000,000.00 for the project. The FY 2025 Budget includes $1,000,000.00 under the Capital Projects Funds - Capital Outlay Account No. 08-34-53-4801 for the construction phase of the Project. Staff recommends awarding the Police Station HVAC Improvements Project to F.E. Moran, Inc. of Northbrook, Illinois, for a total contract amount not to exceed $923,000.00, which includes Base Bid and Alternate No. 1, and reject Alternate No. 2. ===== PDF PAGE 45 ===== [Extraction: embedded PDF text] CITY OF WEST CHICAGO ACTIONS PROPOSED: Approve Resolution No. 25-R-0042 authorizing the Mayor to execute a Contract with the lowest qualified and responsible bidder, F.E. Moran, Inc. of Northbrook, Illinois, for a Base Bid and Alternate No. 1 contract amount not to exceed $923,000.00 and reject Alternate No. 2 for the Police Station HVAC Improvement Project. COMMITTEE RECOMMENDATION: ===== PDF PAGE 46 ===== [Extraction: embedded PDF text] RESOLUTION NO. 25-R-0042 A RESOLUTION AUTHORIZING THE MAYOR TO EXECUTE A CONTRACT WITH F.E. MORAN, INC. OF NORTHBROOK, ILLINOIS, FOR THE POLICE STATION HVAC IMPROVEMENT PROJECT FOR A BASE BID AND ALTERNATE NO.1 CONTRACT AMOUNT NOT TO EXCEED $923,000.00 AND REJECT ALTERNATE NO. 2 BE IT RESOLVED by the City Council of the City of West Chicago, in regular session assembled, that the Mayor is hereby authorized to execute a Contract with the lowest responsible bidder, F.E. Moran, Inc. of Northbrook, Illinois, for a Base Bid and Alternate No. 1 contract amount not to exceed $923,000.00 for the Police Station HV AC Improvement Project and Reject Alternate No. 2, in substantially the form attached hereto and incorporated herein as Exhibit "A". APPROVED this 16th day of June, 2025. AYES: NAYES: ABSTAIN: ABSENT: Mayor Daniel Bovey ATTEST: Valeria Perez, Executive Office Manager ===== PDF PAGE 47 ===== [Extraction: embedded PDF text] Location Map Police Department HVAC Improvements Project 325 Spencer Street West Chicago, DuPage County Project Location ,..... ~ Spencer St : .< (I) ~ C: 0 1/) ~ ===== PDF PAGE 48 ===== [Extraction: embedded PDF text] KluberArchitects + Engineers www.kluberinc.com May 27, 2025 Mr. Dave Shah Assistant Director Public Works City of West Chicago 475 Main Street West Chicago, Illinois 60185 RE: Bid Results Police Department HVAC Improvements Kluber Project No. 24-473-1569 Dear Mr. Shah, On May 21, 2025, bids were publicly opened and read aloud for the above referenced project. Six contractors chose to submit bids for the project. Two alternates were included in the bid and the City has expressed interest in accepting Alternate No. 1 which includes updating VAV box controls. The low base bid plus alternate one was submitted by 1 Source Mechanical from Dekalb, Illinois in the amount of $770,000.00. The second lowest bid for base bid plus alternate one was submitted by Commercial Mechanical from Dunlap, Illinois in the amount of $834,000.00. The third lowest bid for base bid plus alternate one was submitted by FE Moran from Northbrook, Illinois in the amount of $923,000.00. See attached bid tabulation for details on bid results. We conducted a Contractor Bid Scope Review with the first two low bidders for Base Bid plus Alternate No. 1. Bids submitted by 1 Source Mechanical, Inc. and Commercial Mechanical, Inc. were found to be incomplete. These bidders did not include the required $85,000.00 contingency allowance in their Base bid, therefore, these 2 bidders are disqualified since they did not meet the contract requirements per Specification Section 01 21 00 - Allowances of the bid specifications. We conducted a Contractor Bid Scope Review with the third low bidder, FE Moran for Base Bid plus Alternate No. 1 and believe their Base Bid plus Alternate No. 1 to be responsive and complete. Therefore, the City may wish to award a Contract to FE Moran in the amount of $923,000.00 which would include acceptance of Alternate No. 1 for upgrading the VAV box controls in the amount of $203,000.00. The information contained herein and in the attached bid tabulation and scope review is provided to you for reference and use in the City's decision to award the Contract. Thank you for the opportunity to be of service to the City of West Chicago and we look forward to the successful completion of this project with you. Sincerely, Project Manager Kluber Architects + Engineers Attachments: Bid Tabulation, Bid Scope Reviews Cc: Mehul Patel, Director of Public Works Corporate Office Bloomington Office 41 West Benton Street 2401 East Washington Street Aurora, Illinois 60506 Suite 200-B2 630.4061213 Bloomington, Illinois 61704 309 430 6460 ===== PDF PAGE 49 ===== [Extraction: embedded PDF text] BID TABULATION Contract Type: Single Contract Stipulated Sum KluberArchitects + Engineers Kluber Project No.: 24-473-1569 Project: Police Department HVAC Improvements Date: 05/21/2025 Owner: City of West Chicago Time: 1:30 P~l N 0 ci :z z :,E C "t:I "t:I ยง 0 I n, IXl_, C: Alternate Altrirnate TotJI with Total with _, "t:I I No. 1 No. 2 Alternate No. 1 Alternate No. 2 1 Comments PIJn Holder I location I iii ~ Base Bid I I I i i 111 Sour::e Mechanical, Inc. Dekalb, IL y y y $574,000.00 $196,000.00 $620,000.00 $770,000.00 $1,194,000.00 Bid is incomplete. Bidder disqualified. 2ICommerical Mechanical, Inc. Dunlap, IL y y y $604,000.00 $230,000.00 $603,000.00 $834,000.00 $1,207,000.00 Bid is incomplete. Bidder disqualified. 3IFE Moran Northbrook, IL y y y $720,000.00 $203,000.00 $465,000.00 $923,000.00 $1,185,000.00 Bid is Complete 4IHelm Mechanical !Bridgeview, IL y y y $747,000.00 $238,000.00 $628,000.00 $985,000.00 $1,375,000.00 5jVoris Mechanical, Inc. !Glendale Heights, IL y y y $774,400.00 $233,500.00 $558,10~.oo $1,007,900.00 $1,332,500.00 &!Amber Mechanical Contractors, Inc. !Alsip, IL y y y $883,800.00 $317,000.00 $647,800,00 $1,200,800.00 $1,531,600.00 ===== PDF PAGE 50 ===== [Extraction: embedded PDF text] KluberArchitects + Engineers www.kluberinc.com BID SCOPE REVIEW POLICE DEPARTMENT HVAC IMPROVEMENTS Kluber Project No. 25-473-1569 Contractor: F.E. Moran, Inc. Contact: June Tucker Base Bid Amount: $720,000.00 Alternate No. 1 Amount: $203,000.00 Phone: 630-943-7671 Alternate No. 2 Amount: $465,000.00 Email: June.Tucker@FEMoran.com Total with Alternate No. 1 Amount: $923,000 Total with Alternate No. 2 Amount: $1,185,000.00 Date: May 22, 2025 All Addenda have been included in the bid. Yes All Alternates applicable to your contract package have been acknowledged in the bid. Yes All pertinent Allowances are included in the bid. ($85,000) Yes A bid bond was included in the bid package. Yes Are there any qualifications to the bid? No Are there any material deliveries which you feel could have a negative impact on the project schedule? No Are you aware of any discrepancies and/or have any questions on the bid documents? No SCOPE REVIEW: Base Bid Work: 1. Is the pre-test of the vav box and fan powered box minimum and maximum airflow quantities prior to construction included? Yes. 2. Is Testing and Balancing included in the bid for VAV boxes, RTUs, pumps, etc? Yes. 3. Is the demolition of the boiler room included (Boilers, Pumps, expansion tank, piping, etc). Yes. 4. Is the demolition of the boiler and water heater venting included? Yes. 5. Are two new boilers included in the work? Yes. a. What manufacturer are you proposing to use? Lochinvar. b. What is the lead time of the boiler? 6-7 weeks Corporate Office Bloomington Office 41 W. Benton Street 2401 E Washington Street, Suite 200-82 Aurora, Illinois 60506 Bloomington. Illinois 61704 630.406.1213 309.430.6460 ===== PDF PAGE 51 ===== [Extraction: embedded PDF text] 6. Is the new work in the mechanical room (piping, air separator, expansion tank, pumps, etc) included? Yes. a. What manufacturer of the pumps are you proposing to use? Taco or B&G, Lead time ls 6-7 weeks. 7. Is the new venting for the boilers and existing water heater included? Yes. 8. Will you be able to complete the boiler work by middle to end of October? Yes. 9. Is the associated roof work included? Yes. a. Who is the roofing contractor? TCS. 10. Are two new roof top units included? Yes. a. What manufacturer are you proposing to use? Aaon b. What is the estimated lead time for the RTU? 16-18 weeks. c. Are adapter roof cubs included? Yes. 11. Are modifications to hot water piping for the new RTU heating coils included (new control valves, specialties) Yes. 12. Is draining and storing the glycol heating water during modifications to that system included? Yes. 13. Is draining, cleaning, and flushing the entire hydronic system included? Yes. 14. Is the temperature control work included in the bid (rooftop units, boilers, pumps, control valves) Yes. 15. Who is the proposed temperature control contractor? ICT or I8S. 16. Is the electrical work included in the bid? Yes. 17. Who is the proposed electrical contractor? Austln electric or Glow electric. Alternate-No. _1: 1. Is the additional temperature control work included in the bid? (New controllers for VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT or lBS. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is associated ceiling removal and re-installation included in the bid? Yes. Alternate No. 2: 1. Is the additional temperature control work included in the bid? (New controllers for new VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT or IBS. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is the removal of VAV and Fan-powered boxes included in the bid? Yes. 5. Are new VAV boxes with electric heat included in the bid? Yes. 6. Are new Fan-powered boxes included in the bid? Yes. 7. Are duct modifications for the new VAV & Fan-powered boxes included in the bid? Yes. 8. Is additional electrical work included in the bid including upgrading the electrical service and wiring for new VAV boxes? Yes. a. Is the electrical contractor the same as the base bid work? Austin electric or Glow electric. The above constitutes Kluber, Inc. interpretation of the Bid Scope Review telephone call on May 22, 2025. Any changes or discrepancies shall be received by Kluber, Inc. in writing within five business days. ===== PDF PAGE 52 ===== [Extraction: embedded PDF text] KluberArchitects+ Engineers www.kluberinc.com BID SCOPE REVIEW POLICE DEPARTMENT HVAC IMPROVEMENTS Kluber Project No. 25-473-1569 Contractor: 1 Source Mechanical Inc. Contact: Dan Bargiel Base Bid Amount: $574,000.00 Phone: 815-517-0501 Alternate No. 1 Amount: $196,000.00 Email: samc@1sourcemechanical.net Alternate No. 2 Amount: $620,000.00 Total with Alternate No. 1 Amount: $770,000.00 Total with Alternate No. 2 Amount: $1,194,000.00 Date: May 22, 2025 All Addenda have been included in the bid. Yes All Alternates applicable to your contract package have been acknowledged in the bid. Yes All pertinent Allowances are included in the bid. ($85,000) No A bid bond was included in the bid package. Yes Are there any qualifications to the bid? No Are there any material deliveries which you feel could have a negative impact on the project schedule? No Are you aware of any discrepancies and/or have any questions on the bid documents? No SCOPE REVIEW: Base Bid Work: 1. Is the pre-test of the vav box and fan powered box minimum and maximum airflow quantities prior to construction included? Yes. 2. Is Testing and Balancing included in the bid for VAV boxes, RTUs, pumps, etc? Yes. 3. Is the demolition of the boiler room included (Boilers, Pumps, expansion tank, piping, etc). Yes. 4. Is the demolition of the boiler and water heater venting included? Yes. 5. Are two new boilers included in the work? Yes. a. What manufacturer are you proposing to use? Lochinvar. b. What is the lead time of the boiler? The contractor will reach out to Lochinvar. Corporate Office Bloomington Office 41 W. Benton Street 2401 E Washington Street, Suite 200-B2 Aurora, Illinois 60506 Bloomington, Illinois 61704 630.406.1213 309.430.6460 ===== PDF PAGE 53 ===== [Extraction: embedded PDF text] 6. Is ihe new work in ihe rnecr1anicai room (piping, air separator, expansion tank, pumps, etc) included? Yes. a. What manufacturer of the pumps are you proposing to use? Armstrong. 7. Is the new venting for the boilers and existing water heater included? Yes. 8. Will you be able to complete the boiler work by middle to end of October? Yes. 9. Is the associated roof work included? Yes. a. Who is the roofing contractor? Knickerbocker Roofing. 10. Are two new roof top units included? Yes. a. What manufacturer are you proposing to use? Trane. b. What is the estimated lead time for the RTU? The contractor will reach out to Trane. c. Are adapter roof cubs included? Yes. 11. Are modifications to hot water piping for the new RTU heating coils included (new control valves, specialties) Yes. 12. Is draining and storing the glycol heating water during modifications to that system included? Yes. 13. Is draining, cleaning, and flushing the entire hydronic system included? Yes. 14. Is the temperature control work included in the bid (rooftop units, boilers, pumps, control valves) Yes. 15. Who is the proposed temperature control contractor? ICT. 16. Is the electrical work included in the bid? Yes. 17. Who is the proposed electrical contractor? Lohbauer Electric. -Alternate-No. 1-: 1. Is the additional temperature control work included in the bid? (New controllers for VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is associated ceiling removal and re-installation included in the bid? Yes. ' Alternate No. 2: 1. Is the additional temperature control work included in the bid? (New controllers for new VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is the removal of VAVand Fan-powered boxes included in the bid? Yes. 5. Are new VAV boxes with electric heat included in the bid? Yes. 6. Are new Fan-powered boxes included in the bid? Yes. 7. Are duct modifications for the new VAV & Fan-powered boxes included in the bid? Yes. 8. Is additional electrical work included in the bid including upgrading the electrical service and wiring for new VAV boxes? Yes. a. Is the electrical contractor the same as the base bid work? Yes. References: Will Savage, Maintenance Director (630-971-1675) - Lisle library 1. What was the Contractor work scope? Replacement of 4 condensing units and re-piping them. 2. Did the Contractor adequately staff the project? Yes. 3. Was the materials and workmanship in compliance with the contract documents? Yes. 4. Did the Contractor cause any delays to the project? Long lead times have Jed to delays, but they were not caused by the contractors. ===== PDF PAGE 54 ===== [Extraction: embedded PDF text] 5. Did the Contractor work to actively resolve any problems? No problems occurred with their work. Contractors have assisted them with other problems unrelated to their work. 6. Did the Contractor coordinate and cooperate with other contractors and suppliers? Yes. 7. Would you recommend them on future work? Yes. 8. Any additional comments? No. The above constitutes Kluber, Inc. interpretation of the Bid Scope Review telephone call on May 22, 2025. Any changes or discrepancies shall be received by Kluber, Inc. in writing within five business days. Bid is incomplete and bidder is disqualified. ===== PDF PAGE 55 ===== [Extraction: embedded PDF text] KluberArchitects+ Engineers www.kluberinc.com BID SCOPE REVIEW POLICE DEPARTMENT HVAC IMPROVEMENTS Kluber Project No. 25-473-1569 Contractor: Commercial Mechanical Inc. Contact: Luke Murphy Base Bid Amount: $604,000.00 Phone: 309-243-7768 Alternate No. 1 Amount: $230,000.00 Alternate No. 2 Amount: $603,000.00 Total with Alternate No. 1 Amount: $834,000.00 Total with Alternate No. 2 Amount: $1,207,000.00 Date: May 23, 2025 All Addenda have been Included In the bid. Yes All Alternates applicable to your contract package have been acknowledged in the bid. Yes All pertinent Allowances are included in the bid. ($85,000) No A bid bond was included in the bid package. Yes Are there any qualifications to the bid? No Are there any material deliveries which you feel could have a negative impact on the project schedule? No Are you aware of any discrepancies and/or have any questions on the bid documents? No SCOPE REVIEW: Base Bid Work: 1. Is the pre-test of the vav box and fan powered box minimum and maximum airflow quantities prior to construction included? Yes. 2. Is Testing and Balancing included in the bid for VAV boxes, RTUs, pumps, etc? Yes. 3. Is the demolition of the boiler room included (Boilers, Pumps, expansion tank, piping, etc). Yes. 4. Is the demolition of the boiler and water heater venting included? Yes. 5. Are two new boilers included in the work? Yes. a. What manufacturer are you proposing to use? Lochinvar. b. What is the lead time of the boiler? The contractor will review. Corporate Office Bloomington Office 41 W. Benton Street 2401 E Washington Street, Suite 200-B2 Aurora, Illinois 60506 Bloomington, Illinois 61704 630.406.1213 309.430.6460 ===== PDF PAGE 56 ===== [Extraction: embedded PDF text] 6. Is the new work in the mechanical room (piping, air separator, expansion tank, pumps, etc) included? Yes. a. What manufacturer of the pumps are you proposing to use? Armstrong 7. Is the new venting for the boilers and existing water heater included? Yes. 8. Will you be able to complete the boiler work by middle to end of October? Yes. 9. Is the associated roof work included? Yes. a. Who is the roofing contractor? Anthony roofing. They can honor the roofing warranty. 10. Are two new roof top units included? Yes. a. What manufacturer are you proposing to use? Aaon. b. What is the estimated lead time for the RTU? 16-18 weeks c. Are adapter roof cubs included? Yes. 11. Are modifications to hot water piping for the new RTU heating coils included (new control valves, specialties) Yes. 12. Is draining and storing the glycol heating water during modifications to that system included? Yes. 13. Is draining, cleaning, and flushing the entire hydronic system included? Yes. 14. Is the temperature control work included in the bid (rooftop units, boilers, pumps, control valves) Yes. 15. Who is the proposed temperature control contractor? ICT. 16. Is the electrical work included in the bid? Yes. 17. Who is the proposed electrical contractor? Lohbauer Electric. Alternate No. 1: 1. Is the additional temperature control work included in the bid? (New controllers for VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is associated ceiling removal and re-installation included in the bid? Yes. Alternate No. 2: 1. Is the additional temperature control work included in the bid? (New controllers for new VAV boxes & FPBs, new control valves, thermostats, removal of pneumatic tubing, etc.) Yes. a. Who is the temperature control contractor? ICT. 2. Are the pipe modifications for the fin tube, unit heaters, fan powered boxes, etc included in the bid? This includes replacement of pipe specialties and new control valves? Yes. 3. Is the removal of the air compressor, filter dryer, etc included in the bid? Yes. 4. Is the removal of VAV and Fan-powered boxes included in the bid? Yes. 5. Are new VAV boxes with electric heat included in the bid? Yes. (Titus Boxes) 6. Are new Fan-powered boxes included in the bid? Yes. 7. Are duct modifications for the new VAV & Fan-powered boxes included in the bid? Yes. 8. Is additional electrical work included in the bid including upgrading the electrical service and wiring for new VAV boxes? Yes. a. Is the electrical contractor the same as the base bid work? Yes. The above constitutes Kluber, Inc. interpretation of the Bid Scope Review telephone call on May 23, 2025. Any changes or discrepancies shall be received by Kluber, Inc. in writing within five business days. Bid is incomplete and bidder is disqualified.