===== PDF PAGE 36 ===== [Extraction: OCR (rendered-page OCR)] CITY OF WEST CHICAGO _ INFRASTRUCTURE COMMITTEE __ AGENDA ITEM SUMMARY __ ITEM TITLE: AGENDA ITEM NUMBER: 7.B. Resolution No. 26-R-0011 — Contract Award — Plote Construction Inc. for the 2026 Industrial Streets | COMMITTEE AGENDA DATE: February 5, 2026 Improvement Project - Phase A — Downs Drive and Western | COUNCIL AGENDA DATE: March 2, 2026 Drive in an Amount Not to Exceed $7,641,570.50 STAFF REVIEW: Mehul T. Patel, P.E., CFM- Director of Public Works SIGNATURE APPROVED BY INTERIM CITY ADMINISTRATOR: Tia Messino SIGNATURE ITEM SUMMARY: Many roadway segments in the City’s industrial areas require complete roadway reconstruction and underground utility improvements. These improvements are identified in the City’s 5-Year Recommended Roadway Improvement Program in FY 2026, FY 2027, and FY 2028. The Industrial Streets Improvement Program consists of Phase A, Phase B, and Phase C, as denoted in the enclosed location map. 2026 Industrial Streets Improvement Project - Phase A — Downs Drive and Western Drive (Project) is located on Downs Drive and Western Drive from Industrial Drive to Kress Road, as denoted in the enclosed location map. The scope of the project includes full-depth Portland cement concrete (PCC) roadway reconstruction, proposed curb and gutter, proposed sidewalk, including pedestrian access at the existing at-grade railroad crossings, driveway removal and replacement, water main replacement, new street lighting, and miscellaneous utility structure adjustments as denoted in the Project plans and specifications. The net length of roadway improvements is approximately 0.953 miles or 5,034 feet. The construction is anticipated to begin in Spring 2026 and is expected to be completed in October 2026, weather permitting. The Project will be funded through municipal bonds, which will be presented for the City Council's consideration under a separate Agenda. The Project was advertised for public bids in the Daily Herald and on an online bidding platform, QuestCDN, on January 6, 2026. Staff opened bids on January 27, 2026, and below are the bid results: BID CONTRACTOR SUBMITTAL AMOUNT Plote Construction Inc. $7,641,570.50 A Lamp Concrete Contractors, Inc $7,697,909.25 Acura, Inc $8,316,869.32 R.W. Dunteman Co. $8,379,000.00 John Neri Construction Co. $9,017,849.00 Alliance Contractors, Inc. $9, 156,969.69 Everlast Blacktop, Inc. $9,333,473.10 Martam Construction, Inc. $9,993,035.80 Swallow Construction Corp. $10,255,343.15 ENGINEER’S ESTIMATE | $7, 166,971.00 [ O}O;/N/ OD) om) &/@w)/ my) — The FY 2026 Budget includes $6,122,300.00 under Capital Projects Fund Account No. 08-34-53-4807. Plote Construction Inc. of Hoffman Estates, Illinois, submitted the lowest and most qualified bid in the amount of $7,641,570.50, which is $474,599.50 or approximately 6.6% higher than the engineer’s estimated cost of ===== PDF PAGE 37 ===== [Extraction: OCR (rendered-page OCR)] CITY OF WEST CHICAGO $7,166,971.00. Furthermore, Plote’s bid is $1,519,270.50 or approximately 24.8% higher than the FY 2026 budgeted amount of $6,122,300.00. The lowest responsible bid from Plote is 24.8% higher than the budgeted amount due to the widening of Downs Drive by an additional eight feet as required by the City Code of Ordinance, Appendix B, Article X — Design Standards for industrial or business subdivisions. The widening requirement was discovered during design stages and not anticipated during the FY 2026 budgeting process. The widening of Downs Drive added approximately $383,000.00 to the project's overall requirement. In addition, actual costs for PCC pavement construction and the watermain installation were higher than originally anticipated across all the bidders. The overage of $1,519,270.50 will be funded through additional municipal bonds in FY 2026. To offset the overage, the Design Engineering and Construction Engineering for Phases A, B, and C will be funded through the Capital Projects Funds, instead of the municipal bonds as originally anticipated. The cost of design and construction engineering across Phases A, B, and C is estimated at $2,349,675.00. The City has previously contracted with Plote to perform similar work, including the 2024 Harvester Road Reconstruction Project, which was completed satisfactorily. In addition, Plote is registered with the Illinois Department of Transportation as a prequalified contractor. Staff recommends awarding the 2026 Industrial Streets Improvement Project - Phase A — Downs Drive and Western Drive to the lowest responsible bidder, Plote Construction Inc., for a bid amount not to exceed $7,641,570.50. The contract award is contingent on issuance of the General Obligation bonds. ACTIONS PROPOSED: Approve Resolution No. 26-R-0011 authorizing the Mayor to execute a Contract with the lowest responsible bidder, Plote Construction Inc. of Hoffman Estates, Illinois, for the 2026 Industrial Streets Improvement Project - Phase A — Downs Drive and Western Drive in an amount not to exceed $7,641 ,570.50. COMMITTEE RECOMMENDATION: The Infrastructure Committee voted 5-0 for approval.