===== PDF PAGE 122 ===== [Extraction: embedded PDF text] CITY OF WEST CHICAGO INFRASTRUCTURE COMMITTEE AGENDA ITEM SUMMARY ITEM TITLE: AGENDA ITEM NUMBER: -~----Lf:C Rejection of all Bids and Re-bid - York Avenue Area Watermain and Streets Rehabilitation Project COMMITTEE AGENDA DATE: May 7, 2026 COUNCIL AGENDA DATE: May 18, 2026 STAFF REVIEW: Mehul T. Patel, P.E., CFM, Director of Public Works SIGNATURE _________ _ APPROVED BY CITY ADMINISTRATOR: Viviana Ramirez SIGNATURE _________ _ ITEM SUMMARY: In April 2025, the City was awarded Community Development Block Grant (CDBG) funding from DuPage County for the York Avenue Area Watermain and Streets Rehabilitation Project (Project) in the amount not to exceed $600,000.00. Subsequently, the City entered into an Intergovernmental Agreement (IGA) with DuPage County on March 3, 2026, for acceptance of grant funds for the Project. The IGA requires the City to complete the Project and expend the full CDBG funding amount by February 26, 2027. The Project limits are on York Avenue between the dead end and Oakwood Avenue, Garden Street between Washington Street and Grand Lake Boulevard, Virgie Place between Oakwood Avenue and lngalton Avenue, and lngalton Avenue between Washington Street and Grand Lake Boulevard, as denoted in the enclosed location map. The net length of roadway improvements is approximately 5,740 feet or 1.09 miles. The scope of the Project includes the installation of a new 8" ductile iron water main and the associated appurtenances, approximately 90 lead water service line replacements, pavement milling, hot-mix asphalt (HMA) binder and surface course installation, spot Portland Cement Concrete (PCC) curb and gutter removal and replacement, mid-block PCC sidewalk removal and replacement, ADA sidewalk curb ramp, parkway restoration, manhole structure repair and adjustments, thermoplastic pavement markings, and miscellaneous work necessary to complete the Project. The request for bids was advertised in the Daily Herald and on an online bidding platform QuestCDN on April 7, 2026. Staff opened bids on April 28, 2026, and below are the bid results: BASE BID RANK CONTRACTOR SUBMITTAL (BASE BID) AMOUNT C. Szabo Contracting, Inc. $4,229,975.00 1 Martam Construction, Inc. $5,364,867.31 2 Swallow Construction Co. $5,563,084.09 3 ENGINEER'S EST/MA TE $4,573, 135. 77 NIA The FY 2026 budget includes $1,706,500.00 under the Capital Projects Fund Account No. 08-34-53-4807, $1,409,200.00 under the Water Fund Account No. 06-34-47-4806, and $50,000.00 under the Sewer Fund Account No. 05-34-43-4806, for a total of $3,165,700.00 for the Construction of the Project. The responsible low bidder, C. Szabo Contracting, lnc.'s bid amount of $4,229,975.00 was $1,064,275.00 or approximately 34% over the budget amount of $3,165,700.00. Staff believe that the increases in fuel cost, material costs, industry workload and more than expected lead service lines within Project limits are the biggest factors for inflated bids. Furthermore, Staff discussed the project with the DuPage County Community Development Commission to determine if there are mechanisms in place to request additional grant funds or to reduce the Project scope to better align the Project with the approved FY 2026 budget. The request for additional grant funding would require re- application and evaluation which would delay the Project by an additional two years, pending County Board approval. ===== PDF PAGE 123 ===== [Extraction: embedded PDF text] CITY OF WEST CHICAGO The County and staff mutually agreed on the reduction of the scope to keep the Project on schedule. Proposed changes in Project scope will require an amendment to the IGA, including a necessary time extension to complete and close out the Project in FY 2027. The scope change and the amendment to the IGA must be approved by the County Board before the City can rebid the Project, which is anticipated in July 2026, with a contract award recommendation in August 2026, under a separate agenda item. Staff recommends rejecting all bids and rebidding the Project in Summer 2026 to receive bids that better align with the FY 2026 budget. ACTIONS PROPOSED: Reject all bids. COMMITTEE RECOMMENDATION: ===== PDF PAGE 124 ===== [Extraction: embedded PDF text] . r,. - - ---, lRP 11 III YORK AVENUE AREA WaterReplacementMain WATER MAIN AND STREETS REHABILITATION PROJECT ... ..,... CITY OF WEST CHICAGO TRACT 8415.04 LOCATION MAP flNN!~Jr,.fM, 'NEST ~CAGO IL60185 f aJC l~J.:n.rl BLOCK GROUP #2 _ 2 or- 4