| 2.A — August 6, 2026 Infrastructure Committee minutes |
Approve the Committee’s draft record of its prior meeting. |
No direct City expenditure identified. |
Likely non-discretionary / administrative. Approval maintains the Committee’s official meeting record. |
| 4.A — Two 2027 Ford F600 snow-and-dump trucks |
Recommend purchase of two chassis from Haggerty Ford and two Sourcewell-priced upfits from Monroe Truck Equipment for replacement Streets Division units 742 and 743. |
$289,602 total: $123,198 for two chassis and $166,404 for two upfits. The replacement budget is $274,200; the $15,402 overage would use $15,700 budgeted for a zero-turn mower that will not be purchased. |
Mixed. Replacing planned plow/dump trucks supports core street operations, but the current action chooses vendors and equipment and reallocates mower funding. Haggerty’s chassis price is $256 each above Olathe Ford’s Sourcewell price under the City’s local-vendor preference policy. |
| 4.B — 2027 Freightliner plow/dump truck |
Recommend one Freightliner chassis from Trans Chicago Truck Group and an upfit from Bonnell Industries to replace unit 750; the current truck would become a Water Division spare. |
$335,335.18 total: $138,922 chassis and $196,413.18 upfit. The replacement budget is $278,000; the $57,335.18 shortage would be covered by deferring unit 654, for which $62,600 is budgeted. Pricing may change before the estimated October 2027 delivery. |
Mixed. This is a planned replacement for snow and utility operations, but it commits a large purchase, defers another vehicle, and may require a later change order if delivery pricing changes. |
| 4.C / Resolution 26-R-0067 — FY2027 carbon dioxide |
Recommend the first one-year contract extension with MacCarb at the existing delivered price of $0.135 per pound for water-treatment use. |
Not to exceed $64,800. Staff estimates 240 tons in FY2027 and says adequate FY2027 Water Fund chemical-account funding will be budgeted. |
Likely non-discretionary / utility operations. The extension maintains an existing treatment chemical at the current unit price under an approved contract option. |
| 4.D / Resolution 26-R-0068 — FY2026 carbon-dioxide change order |
Recommend adding carbon-dioxide capacity because finished-water production is up about 3.5% and chemical dosage is up about 5%. |
$10,000 increase, from $48,600 to a revised $58,600; adequate FY2026 Water Fund chemical-account funding is available. |
Likely non-discretionary / utility operations. The change order maintains chemical inventory for the municipal water-treatment process in response to higher actual use. |
| 4.E / Resolution 26-R-0069 — FY2027 sodium hypochlorite |
Recommend the first one-year extension with Alexander Chemical for the primary water disinfectant at a 2% higher unit price of $0.162 per pound and an estimated 360 tons. |
Not to exceed $116,769. Adequate FY2027 Water Fund chemical-account funding will be budgeted. Multiplying the stated 360 tons by $0.162 per pound yields $116,640, $129 below the proposed cap. |
Likely non-discretionary / utility operations. The extension continues a required treatment chemical under an existing contract option, though the cap-versus-quantity arithmetic should be confirmed. |
| 4.F / Resolution 26-R-0070 — FY2027 hydrated lime |
Recommend the first one-year extension with Graymont Western Lime for water softening at a 2% higher unit price of $308.04 per ton and an estimated 1,450 tons. |
Not to exceed $446,658, which equals 1,450 tons at $308.04 per ton. Adequate FY2027 Water Fund chemical-account funding will be budgeted. |
Likely non-discretionary / utility operations. The extension continues a required water-treatment chemical under an existing contract option. |
| 4.G / Resolution 26-R-0071 — Underground-storage-tank environmental services |
Recommend Amendment No. 2 with Resource Consulting for additional soil borings, analysis, planning, oversight, project management, completion reporting, and reimbursement work required after Illinois EPA rejected the corrective-action plan. |
$12,500 amendment; revised professional-services cap $81,900. The Capital Projects Fund has $36,985 available. Some eligible costs may be reimbursed, but Illinois EPA will determine the amount; the underlying project has a $10,000 deductible. |
Likely non-discretionary / regulatory and environmental compliance. The amendment responds to Illinois EPA requirements for a longstanding petroleum release before corrective work and reimbursement can proceed. |
| 4.H / Resolution 26-R-0072 — Waste-lime-sludge removal |
Recommend the low bid from Synagro Central at $55 per wet ton for up to 9,600 tons, using land application rather than landfill disposal. |
Contract cap $528,000. FY2026 spending is limited to the $363,000 budget, enough for 6,600 tons; the remaining estimated 3,000 tons would carry into 2027 subject to contract terms and appropriations. The second bid was $551,232. |
Likely non-discretionary / water-treatment maintenance. Removing accumulated treatment residuals is an operational need, although the Committee should scrutinize the two-year funding plan and weather-dependent schedule. |
| 4.I / Resolution 26-R-0073 — Sanitary-sewer rehabilitation |
Recommend an OMNIA cooperative contract with Hoerr Construction for 730 feet of cured-in-place sewer lining and epoxy lining at lift stations 2 and 7. |
Not to exceed $308,460, including a $30,000 contingency, within a $500,000 FY2026 Sewer Fund budget. |
Likely non-discretionary / core infrastructure maintenance. The project repairs previously identified sewer defects and corrosion using an existing competitively procured cooperative contract. |